Revitalizing a Dilapidated Home: The Hammil Project

The Project

When we first started this project with the client, the initial scope of work was intended for a foundation repair. However, it eventually escalated into a full house remodel involving structural replacements for the floor joists and trusses as well as aesthetic elements for the remodel, including new flooring, countertops, and more.

Bathroom

At a Glance

Project Type

A New House

Location

Camas, WA

Cost

Approximately $350,000

Start Date

6/10/2019

Project Details

  • Type: Extensive renovations were made, including floor joist and truss replacements.
  • Size: The home is approximately 2000 sq ft.
  • Materials: Virtually everything in the house was replaced with new materials.
  • Features: Brand new flooring, trusses, bathroom remodel, kitchen remodel, expanded living room, siding, and more. A new house from top to bottom.
  • Benefits: This project was transformed from a rundown house with severe structural issues into a completely revitalized home.

Before Project Conditions

The initial state of the house:

  • Structural Issues: There were floor joists and foundation failures with significant structural damage. The floor, siding, and porch were failing and rotting. We had to tear a lot down and competently rebuild.
  • Aesthetic Issues: There were noticeable rotting issues and makeshift additions like an old chicken coop. This was a large part of why we needed to start from scratch on a lot of areas.

Challenges Faced

  • Permitting Issues: The project faced several challenges associated with obtaining county permits. One of the primary issues was the occurrence of delays which hindered the progress of the project. These delays were often brought about by bureaucratic procedures or unexpected issues that arose during the process of obtaining the permits.
  • Environmental Challenges: The team worked through winter without walls and used the fireplace for warmth.
  • External Factors: The project timeline was significantly affected due to the shutdowns instigated by the COVID-19 pandemic. These shutdowns, which were a necessary response to a global health crisis, resulted in the closure of many businesses and put a halt to a multitude of projects, ours included. Our original schedule had to be altered as we had to abide by the safety guidelines and lockdown measures.

During the Project

The major phases and adjustments made:

  • Expanded Scope: With the new permits, we needed to bring the whole house up to today’s code. This required us to redo the opposite side of the house. We removed and added a new foundation and redid the exterior walls. This was an obligatory action initiated by the regulatory requirements of the contemporary building codes.
  • Complex Tasks: It was difficult to hold the roof trusses during demolition in adverse weather conditions.
Interior Construction
Construction
Exterior Construction

Project Length and Timeline

  • Duration: The project took approximately 9 months, with 3 months of delay due to COVID-19 and permit-related issues.
  • Completion: Our team was able to complete the project just in time for summer so our clients were able to enjoy their newly remodeled home.

After Project Results

  • Outcome: The house underwent a complete transformation that turned it into a contemporary home. This total makeover wasn’t confined to just one area; it spanned from top to bottom. Every inch of the house was meticulously worked on. The ceilings, the walls, the floors – nothing was left untouched. The dated architecture and old-fashioned designs were discarded, replaced with a modern aesthetic that breathed new life into the structure. The transformation was so thorough that the house, in its new avatar, felt like a modern home through and through.
  • Client Satisfaction: Our team recently had an interaction with one of our esteemed clients. After a thorough review and assessment of our services, we were delighted to receive feedback from them. The client expressed satisfaction and pleasure with our services, applauding our meticulous attention to detail and timely delivery. The positive feedback, which was filled with praises and commendations, gave us reassurance about the quality of our work and served to motivate our team to continue to strive for excellence. It was a rewarding experience that not only boosted our morale but also confirmed our commitment to providing top-notch services to our clients.
Kitchen Remodeling Icon

Anything can be done with a house if you have enough time and money when it is approached by a diligent and resourceful company like Amundson Construction

We overcome substantial challenges to deliver a high-quality outcome.

Lessons Learned

The experience and insights gained:

  • Working with Authorities: In our endeavors, we encountered a multitude of obstacles and difficulties when it came to navigating the complex and often confusing maze of county regulations. These regulations, which are often intricate and layered, presented us with numerous challenges that we had to tackle. The task was not simple. It required deep understanding and a thorough analysis of the regulatory framework that the county had put in place.
  • Seasonal Considerations: We managed construction in adverse weather conditions.
  • Team Dynamics: In our organization, we deeply value and actively recognize the hard work, commitment, and excellent performance of each member of our crew. We understand the significance of their individual roles and the impact they have on the overall success of our operations. We don’t just stop at acknowledging their efforts, but we also take it a step further by continuously fostering an environment that encourages teamwork. We believe that only through effective collaboration and unity can we truly unlock our potential and achieve our collective goals.

Conclusion

The project’s success and key takeaways:

  • Achievements: In the course of our project, we encountered and triumphed over substantial challenges. These difficulties ranged from technical issues, time constraints, and resource limitations, to unexpected setbacks that emerged at various stages of the project. Our team, however, remained steadfast and committed, demonstrating resilience and adaptability in the face of adversity.
  • Final Thoughts: Anything can be done with a house if you have enough time and money when it is approached by a diligent and resourceful company like Amundson Construction.